Wednesday, April 30, 2008
No date yet....
Ms CSR also told me that B-bank has now introduced a website for us to check the progress of our building, similar to what PD have been doing, which is great. Not that it is that usefull for us as we currently live 2 minutes away from our block, we can check the progress "live" everyday
Monday, April 28, 2008
Building permit issued
Straight after that we called the builder to ask the date for the site start .......Ms CSR told us that she'll know by wednesday when she see the site supervisor then....
Ohhh can't wait .........
Tuesday, April 15, 2008
Building Permit application
Building permit has also been submitted with the council office....i guess now we can just wait and hope that the council will approve the permit quickly.
Fast forward to the future....
At last we decided to have a blog on our voyage to build our dream home... where should we begin....ok here we go
June 2007 - found a good sized flat block of land with an old house on it, put an offer to and got accepted and settlement in October.
July 2007 - finally we decided to build with burbank because we love the floorplan. Initially we want to build with PD but they say they don't build in the our area... Meet quickly in the morning with the sales rep at burbank's display house and paid a $1,000 deposit to lock the promotion price.
October 2007 - Burbank contacted us and arranged a tender and colour selection appointment. we were a bit suprised by the site costs which adds up to $20,000 due to demolition of the old house on the land. Later we accepted the tender and make necessary variations and additions to the house.
Land was finally settled as well....
December 2007 - Finally decided to go ahead with a demolition company to demolish the house and it was all done a week before Xmas and before the big storm that hit melbourne badly.
January 2008 - Nothing much happening, we keep on hasseling the builder with the final tender .....
February 2008 - Final tender issued
March 2008 - Finally the contract is signed and we paid the 10% deposit. The builder found out that we need to get dispensation from the council because the garage wall height is 190mm over the limit.
The front of the old house:
The front of the old house after asbestos been removed:
Demolition in progress:
The finished product (from the back of the block)